Port of Rauma 12 m fairaway and deepened quays – preliminary timetable

The fairway and container and bulk berth investments are soon completed and ready to be taken in use.

Rihtniemi fairway has been deepened and all the works at the fairway has already been finalized. The 12-meter fairway will be officially taken in use on December 15th, 2017. At the same time the deepened Ro-Ro 7 berth will be taken in use. Maximum allowed draught to the Ro-Ro 7 berth given by the Port Authority will be 12 meters.

Container terminal investment will be finalized by the end of year 2017. Container berth will be taken in use on January 1st, 2018. Maximum allowed draught to the con-tainer berth given by the Port Authority will be 12 meters.

Deepening of the bulk berth has taken more time than expected and work will contin-ue thru January 2018. According to the contractor, the bulk berth can be taken in use with 12-meter maximum draught on February 1st, 2018.

The timetable for container berth and bulk berth is still preliminary. The official dates when these berths can be taken in use, will be informed by Port of Rauma.

More information:

Port Engineer Timo Metsäkallas, tel. 050 303 9706