Project objectives
- Develop port infrastructure by removing the current bottlenecks of insufficient cargo field area and congestion in the port
- Enable meeting the current and future demand of increased cargo volumes of break bulk, especially from the forest industry
- Allow construction of a new quay with several berths for large-sized bulk cargo vessels to handle the expected growth
- Increase the efficiency of break bulk maritime transport and further decrease the emitted emissions per transported cargo tonne
Project activities
Development of cargo field by dredging and filling
PROJECT INFO
Financier

Duration
1.5.2019 – 31.08.2022
Budget
total budget 11 843 466 €
CEF-funding 2 383 693 €
More information:
Timo Metsäkallas
timo.metsakallas@portofrauma.com
+358 50 303 9706